The measurement point is where this shows up in program delivery. I stopped reporting adoption from the go-live date and started the clock at each team's first hands-on session. On one rollout the gap was six weeks, and the supposedly late teams were tracking almost exactly on pace once their real start date was used.
The measurement point is where this shows up in program delivery. I stopped reporting adoption from the go-live date and started the clock at each team's first hands-on session. On one rollout the gap was six weeks, and the supposedly late teams were tracking almost exactly on pace once their real start date was used.